https://newsletter.po.creamermedia.com
Deepening Democracy through Access to Information
Home / Statements RSS ← Back
Africa|Coal|Construction|Energy|Eskom|Gas|generation|Infrastructure|Power|Projects|Renewable Energy|SECURITY|Technology|Testing|Infrastructure
Africa|Coal|Construction|Energy|Eskom|Gas|generation|Infrastructure|Power|Projects|Renewable Energy|SECURITY|Technology|Testing|Infrastructure
africa|coal|construction|energy|eskom|gas|generation|infrastructure|power|projects|renewable-energy|security|technology|testing|infrastructure
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Eskom on Kusile Unit 6 unlocking full 9600MW capacity across Eskom’s flagship stations


Close

Eskom on Kusile Unit 6 unlocking full 9600MW capacity across Eskom’s flagship stations

Should you have feedback on this article, please complete the fields below.

Please indicate if your feedback is in the form of a letter to the editor that you wish to have published. If so, please be aware that we require that you keep your feedback to below 300 words and we will consider its publication online or in Creamer Media’s print publications, at Creamer Media’s discretion.

We also welcome factual corrections and tip-offs and will protect the identity of our sources, please indicate if this is your wish in your feedback below.


Close

Embed Video

Eskom on Kusile Unit 6 unlocking full 9600MW capacity across Eskom’s flagship stations

Eskom on Kusile Unit 6 unlocking full 9600MW capacity across Eskom’s flagship stations
Photo by Bloomberg

30th September 2025

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

Eskom is pleased to confirm that Unit 6 at Kusile Power Station has officially entered commercial operation, marking the successful completion of Eskom’s Build Programme. This milestone is a key component of the Generation Recovery Plan and ends the construction of South Africa’s two supercritical coal-fired power stations—Medupi and Kusile.

Together, these stations form the backbone of the country’s baseload electricity supply. With Unit 6 now online, Kusile and Medupi can deliver a combined 9 600MW when operating at full capacity, significantly strengthening South Africa’s electricity supply.

Advertisement

Commercial operation indicates that the unit has passed all required testing and optimisation phases and is now fully integrated into Eskom’s operational fleet. Although the unit has been supplying electricity to the grid since its synchronisation on 23 March 2025, its contribution had not been reflected in official reporting until now. From this point onward, Unit 6’s output will be included in the Energy Availability Factor (EAF) calculations, contributing to Eskom’s overall performance metrics.

This achievement also marks a key milestone in Eskom’s strategic goal to add 2 500MW of new capacity to the grid by March 2025 and represents a major step in completing one of the largest infrastructure projects in South Africa’s history.

Advertisement

“The successful commissioning of Unit 6 adds 800MW to the grid and completes our twelve-unit Megaprojects fleet. We extend our gratitude to employees and contractors for their commitment and perseverance in delivering this milestone. Despite the many challenges along the way, the successful handover of Unit 6 reflects the team’s resilience and dedication. We look forward to the added stability these megawatts will bring,” said Bheki Nxumalo, Eskom Group Executive for Generation.

“Achieving commercial operation of Unit 6 within the planned timeframe is a testament to Eskom’s disciplined execution of the Generation Operational Recovery Plan. This milestone not only completes the Kusile build programme but also reinforces Eskom’s commitment to restoring energy security, enhancing grid stability, and investing in infrastructure that supports South Africa’s long-term economic growth. Since its synchronisation in March, Unit 6 has consistently met performance benchmarks, contributed to grid reliability, and helped meet electricity demand 97% of the time,” said Eskom Group Chief Executive, Dan Marokane.

“Medupi and Kusile will remain central to South Africa’s electricity supply for many years to come. Both stations are designed for an operational lifespan of approximately 50 years. As we celebrate this milestone, we are also accelerating efforts to expand our renewable energy portfolio to complement our baseload infrastructure. This is part of our broader strategy to repower the grid and reduce overall emissions,” added Marokane.

Kusile Power Station is the first in South Africa—and on the African continent—to implement Wet Flue Gas Desulphurisation (WFGD) technology. This ensures compliance with air quality standards and aligns with global best practices to reduce sulphur dioxide emissions.

Eskom remains committed to executing its Generation Operational Recovery Plan, enhancing governance, and future-proofing the organisation to ensure energy security, economic growth, and long-term sustainability for South Africa and the broader sub-Saharan region.

 

Issued by Eskom

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      ARTICLE ENQUIRY      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za