Coal|Coal-fired Power Station|Construction|Contractor|Efficiency|Energy|Engineering|engineering news|Eskom|Generator|Installation|Power|PROJECT|Renewable Energy|Solar|Technology|Training|Turbines|Turbines|Operations
Coal|Coal-fired Power Station|Construction|Contractor|Efficiency|Energy|Engineering|engineering news|Eskom|Generator|Installation|Power|PROJECT|Renewable Energy|Solar|Technology|Training|Turbines|Turbines|Operations
coal|coalfired-power-station|construction|contractor|efficiency|energy|engineering|engineering-news|eskom|generator|installation|power|project|renewable-energy|solar|technology|training|turbines-company|turbines-person|operations
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Embed Video

5

Eskom gears up to start Sere wind farm construction in April

21st January 2013

By: Terence Creamer
Creamer Media Editor

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Construction of Eskom’s 100 MW Sere wind project, which is being developed in Koekenaap, in the Western Cape, is scheduled to begin in April with project funding now fully in place and with a preferred bidder having been identified for the supply and installation of the wind turbines.

However, Eskom is not yet in a position to identify the wind-turbine contractor, with that announcement planned following a World Bank review. The project is being managed in line with the World Bank’s procurement guidelines, owing to the fact that it is being partly funded by the development finance institution.

Advertisement

The Sere wind farm is receiving some of its funding from the $3.75-billion 'Eskom Investment Support Project', approved by the bank in 2010 primarily to support the Medupi coal-fired power station. The package also provides loan funding for Eskom's proposed concentrated solar project (CSP) and a number of energy efficiency programmes.

Funding has also been secured from the Clean Technology Fund (CTF), which is overseen by the World Bank. Funds secured from this source have tenors of up to 40 years at an interest rate of 0.25%.

Advertisement

The South African CTF Investment Plan submission for $500-million included a $350-million request for both the Sere wind farm and Eskom’s proposed 100 MW CSP project. The CTF Trust Fund Committee approved the funding during October 2009 and the investment plan contained a funding allocation of $100-million for Sere and a further $250-million for the CSP project.

In total, the World Bank funding component comprises 32.4% of the overall funding plan for the project, which is situated about 300 km north of Cape Town. A French Development Bank component, meanwhile, comprises 36.7%, while an African Development Bank component makes up 26.8%. The development costs are being carried by Eskom.

The wind turbine-generator contract comprises about 65% of the total capital expenditure and will involve the installation of 46, 2.3 MW turbines.

Still outstanding is the contract for the supply, installation and commissioning of a 132 kV line and a substation that will be sited on the Skaapvlei farm, which is within a 16 km radius of Koekenaap.

Bidding documents for this aspect of the project, which comprises about 8% of the project’s overall value, were released in mid-January and the tender will close on February 22. Eskom expects to award the contract during April.

“The construction schedule of the power line and substation will be parallel to the installation of the wind turbines and the rest of the works. The power line and substation will be ready for the plant commissioning,” Eskom reports in response to questions posed by Engineering News Online.

The current forecast date is for a reliability test to be conducted on the first turbine by April 2014 and on the last turbine by September, when the "collective performance trial" should also be completed.

Eskom expects Sere to have a capacity factor of 34% once fully operational and it says its cost of operations will be “very competitive” when compared with the tariffs published by the Department of Energy, following the first two bid windows for the the Renewable Energy Independent Power Producer Programme.

Once the contracts have been announced, Eskom will engage the preferred bidders to negotiate “acceptable levels of localisation”.

Eskom forecasts that 200 direct jobs will be created during construction, together with up to 2 100 indirect and/or induced jobs.

It also expects that the facility will lead to the creation of about 10 permanent jobs once the plant is fully operational and reports that training has been incorporated as a major feature of the project.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za