https://newsletter.po.creamermedia.com
Deepening Democracy through Access to Information
Home / News / South African News RSS ← Back
Africa|Business|Construction|Contractor|Design|Electrical|Energy|Engineering|Environment|EPCM|Fabrication|Financial|Gold|Health|Infrastructure|Installation|Mining|Power|PROJECT|Renewable Energy|Renewable-Energy|Resources|Road|Safety|SECURITY|Surface|System|Training|Underground|Waste|Contracting|Equipment|Environmental|Infrastructure|Waste|Cables|Operations
Africa|Business|Construction|Contractor|Design|Electrical|Energy|Engineering|Environment|EPCM|Fabrication|Financial|Gold|Health|Infrastructure|Installation|Mining|Power|PROJECT|Renewable Energy|Renewable-Energy|Resources|Road|Safety|SECURITY|Surface|System|Training|Underground|Waste|Contracting|Equipment|Environmental|Infrastructure|Waste|Cables|Operations
africa|business|construction|contractor|design|electrical|energy|engineering|environment|epcm|fabrication|financial|gold|health|infrastructure|installation|mining|power|project|renewable-energy|renewable-energy-company|resources|road|safety|security|surface|system|training|underground|waste-company|contracting|equipment|environmental|infrastructure|waste|cables|operations
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Contract route saves gold project R300m, local tech takes tanks out of critical path


Close

Contract route saves gold project R300m, local tech takes tanks out of critical path

Should you have feedback on this article, please complete the fields below.

Please indicate if your feedback is in the form of a letter to the editor that you wish to have published. If so, please be aware that we require that you keep your feedback to below 300 words and we will consider its publication online or in Creamer Media’s print publications, at Creamer Media’s discretion.

We also welcome factual corrections and tip-offs and will protect the identity of our sources, please indicate if this is your wish in your feedback below.


Close

Embed Video

Contract route saves gold project R300m, local tech takes tanks out of critical path

SGS Bateman MD George Corlett
Department of Mineral Resources and Energy representative George Siwele
Pan African chairperson Keith Spencer
Pan African's project launch covered by Mining Weekly's Martin Creamer. Video: Creamer Media's Shadwyn Dickinson and Nicholas Boyd.
Photo by Creamer Media Chief Photographer Donna Slater
SGS Bateman MD George Corlett
Photo by Creamer Media Chief Photographer Donna Slater
Department of Mineral Resources and Energy representative George Siwele
Photo by Creamer Media Chief Photographer Donna Slater
Pan African chairperson Keith Spencer

7th October 2024

By: Martin Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

JOHANNESBURG (miningweekly.com) – The contract route chosen to recover gold from the mine dumps of the West Rand’s Mogale City reduced the project cost by R300-million.

In addition, the technical prowess of a Krugersdorp fabrication and erection company down the road virtually took the carbon-in-leach (CIL) gold processing tanks out of the project’s critical path, and power supply infrastructure was piggy-backed from another nearby metals company, which provided a valuable electricity offramp for the gold upramp.

Advertisement

A first for Pan African was to go on the engineering, procurement and construction management (EPCM) contracting structure.

“That has saved us about R300-million,” Mogale Tailings Retreatment (MTR) operations manager Oriel Shikwambana highlighted at the operational commissioning of MTR, covered by Mining Weekly. (Also watch attached Creamer Media video.)

Advertisement

The original budget figure was R2.8-billion and opting for EPCM reduced the project budget to R2.5-billion. The timeline was squeezed to 14 months.

More than one-and-a-half-million person hours have been spent in construction on this site, without a single lost-time injury (LTIs). “There were zero LTIs,” SGS Bateman MD George Corlett said to the strongest applause of the day.

Contractually, SGS Bateman was to deliver the project to cold commissioning stage by the already tight October 17 timeline, but managed hot commissioning on October 3, when the first gold was smelted.

“The long hours worked over the entire 22 months of the project show the dedication and commitment to meet the project goals,” Corlett said.

The project is said to have been elevated by a win-win, one-team, open-communication approach of Pan African project manager Brandon Russell, working closely with the SGS Bateman project team leader Charl Botha.

“This is a great opportunity for the area. I know that other companies have looked at retreating the dumps in the area and have passed the opportunity by, whereas Pan African has taken that handle and run with it. The area needs the employment. The rehabilitation of the area will be great and it will be good for our country,” Corlett added.

Originally planned was the creation of 700 jobs, with 500 from the local community, but this has been significantly exceeded, resulting in more than 1 600 employees now being on site and 1 040 of them being drawn from the local community.

Department of Mineral Resources and Energy (DMRE) representative George Siwele spoke of the value of the 20 years of employment that the project is bringing to the area, coupled to the removal of dumps that some regard as a nuisance.

The DMRE contribution, Siwele said, would be in the form of the department's mine, health and safety inspectorate support structure.

He personally represented the mine equipment inspectorate, while the colleagues with him dealt with mining-related issues. An occupational hygiene inspector also formed part of that support system.

“Then my other counterpart colleagues are from a section called mineral regulation dealing with environmental issues and social and labour plans."

Growth was supported through training and certification of a number of qualifications, in direct liaison with the department's Mining Qualifications Authority.

“Social and labour colleagues are best suited in terms of assisting, if you are going to be providing training or assisting upcoming employees in the area, on how best to deal with that fund going forward,” added Siwele, who welcomed Pan African to the DMRE region, which he described as being based in Braamfontein but with DMRE officials available on their cellphones.

THE GOLDEN CITY

Twenty per cent of all the gold ever mined in the world – close to 1.3-billion ounces of the precious metal – was mined on the Witwatersrand, of which Pan African’s MTR operation forms part.

Johannesburg, one of the few cities in the world not situated along a coastline or large river system, was built on underground rivers of gold.

“We’re injecting fresh cash and life into an area that was seemingly written off in terms of degradation and pollution by more than 100 years of mining,” noted Pan African chairperson Keith Spencer.

Left behind is a scarred landscape, affecting thousands of lives in communities built around what many have regarded as worthless, dusty mine dumps, with only liabilities remaining.

“While we’re mining, we’ll rehabilitate the environment, install a renewable-energy facility, plus other improvements that will sustain the land and its communities for a long time,” said Spencer, who promised to process "this waste” profitably for the benefit of all stakeholders.

“This is what it is all about, leaving a positive legacy for future generations,” he highlighted.

No security incidents have been suffered and illegal mining has virtually been managed out of the area completely, Shikwanbana said to applause.

The CIL gold processing tanks were originally in the project’s critical path and their installation would have absorbed considerable management time and capacity until local company Betterect was contacted to make the CIL tanks. Moreover, the bolted design it came up with averted feared flange leaks.

“We set up the CILs without a single leak,” Shikwanbana reported.

“Then we also piggy-backed on the Bright Alloys power supply infrastructure and power is currently being supplied from the Bright Alloys infrastructure.

Another important contributor was DMRE approval of the environmental licence being bang on time, which enabled construction to begin when planned.

“The last point is that we split the acquisition of the electrical cables from the electrical contractor’s scope. Generally, when the electrical contractor comes to do the construction, they come with their own cables.  

“We managed to negotiate because we felt that if we split the cables, we’d be able to acquire them much quicker from our side and then it will also save on cost as well, After we split that, we managed, from an acquisition perspective, to save about a week or so, and also on the cost we saved quite a bit of money as well,” he added.

Processed slimes dam material will initially be deposited into the West Wits openpit.

As cited by Pan African CEO Cobus Loots, the biggest takeaway from what is set to become a hugely profitable operation is that investing in South Africa can bear considerable fruit.

“It’s quite ironic. We’ve been pretty much all over Africa looking for opportunities in terms of expanding our business and ultimately we’ve come back to South Africa and less than an hour from our corporate office, we have 1.1-million ounces of recoverable gold reserve here, and we acquired all of it for just over $1/oz, which is fantastic,”

Payback of the initial investment is expected in two to three years at a time when the gold price is $2 500/oz.

Interestingly, the London- and Johannesburg-listed company has advanced significantly in gold recovery from surface dumps.

Pan African's total gold production is expected to hit the 220 000 oz mark this financial year, with net cash possibly flowing by 2026.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      ARTICLE ENQUIRY      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za